Prim's algorithm

Grow a minimum spanning tree from one vertex: again and again, add the cheapest edge that connects the tree to a vertex outside it.

Time (binary heap) Time (array, dense graphs) Extra space Output
\(O(E \log V)\) \(O(V^2)\) \(O(V + E)\) a minimum spanning tree

The idea

Kruskal builds many little trees and merges them. Prim builds one tree and lets it grow, like a crystal. At each step the tree is one side of a cut, the rest of the graph the other side, and the cheapest edge across that cut is always safe to add (the cut property on the Kruskal page).

To find the cheapest edge leaving the tree quickly, keep the candidate edges in a min-heap. When a vertex joins the tree, push all its edges to vertices still outside. Popped edges whose far end is already inside are skipped.

The code is almost the same as Dijkstra's. The difference is the number used as the key: Dijkstra uses the total distance from the start, Prim only the weight of the last edge.

How it works

  1. Push (0, start, -1).
  2. While the heap is not empty: pop the cheapest (w, v, from); if v is in the tree, skip it. Otherwise add v (and the edge from–v) to the tree, and push (weight, x, v) for every edge to an x not in the tree.

Code

import heapq


def prim(n, edges, start=0):
    """Minimum spanning tree by growing one tree from start: (total weight, edges in the order added)."""
    adj = [[] for _ in range(n)]
    for u, v, w in edges:
        adj[u].append((w, v))
        adj[v].append((w, u))
    in_tree = [False] * n
    pq = [(0, start, -1)]                    # (edge weight, vertex, the tree vertex it hangs from)
    total, chosen = 0, []
    while pq:
        w, v, frm = heapq.heappop(pq)        # the cheapest edge leaving the tree
        if in_tree[v]:
            continue                         # both ends already in the tree: skip
        in_tree[v] = True
        total += w
        if frm != -1:
            chosen.append((frm, v, w))
        for w2, x in adj[v]:
            if not in_tree[x]:
                heapq.heappush(pq, (w2, x, v))
    return total, chosen


if __name__ == "__main__":
    edges = [(0, 1, 4), (0, 7, 8), (1, 2, 8), (1, 7, 11), (2, 3, 7), (2, 8, 2), (2, 5, 4), (3, 4, 9),
             (3, 5, 14), (4, 5, 10), (5, 6, 2), (6, 7, 1), (6, 8, 6), (7, 8, 7)]
    total, chosen = prim(9, edges)
    print(total)
    print(chosen)
import java.util.ArrayList;
import java.util.List;
import java.util.PriorityQueue;

public class Prim {
    /** Minimum spanning tree by growing one tree from start; returns its weight, fills chosen in order. */
    static int prim(int n, int[][] edges, int start, List<int[]> chosen) {
        List<List<int[]>> adj = new ArrayList<>();
        for (int i = 0; i < n; i++) adj.add(new ArrayList<>());
        for (int[] e : edges) { adj.get(e[0]).add(new int[]{e[2], e[1]}); adj.get(e[1]).add(new int[]{e[2], e[0]}); }
        boolean[] inTree = new boolean[n];
        // (edge weight, vertex, the tree vertex it hangs from); ties broken like Python's tuples
        PriorityQueue<int[]> pq = new PriorityQueue<>((a, b) ->
            a[0] != b[0] ? Integer.compare(a[0], b[0]) : a[1] != b[1] ? Integer.compare(a[1], b[1]) : Integer.compare(a[2], b[2]));
        pq.add(new int[]{0, start, -1});
        int total = 0;
        while (!pq.isEmpty()) {
            int[] top = pq.poll();                    // the cheapest edge leaving the tree
            int w = top[0], v = top[1], from = top[2];
            if (inTree[v]) continue;                  // both ends already in the tree: skip
            inTree[v] = true;
            total += w;
            if (from != -1) chosen.add(new int[]{from, v, w});
            for (int[] e : adj.get(v))
                if (!inTree[e[1]]) pq.add(new int[]{e[0], e[1], v});
        }
        return total;
    }

    public static void main(String[] args) {
        int[][] edges = {{0, 1, 4}, {0, 7, 8}, {1, 2, 8}, {1, 7, 11}, {2, 3, 7}, {2, 8, 2}, {2, 5, 4}, {3, 4, 9},
            {3, 5, 14}, {4, 5, 10}, {5, 6, 2}, {6, 7, 1}, {6, 8, 6}, {7, 8, 7}};
        List<int[]> chosen = new ArrayList<>();
        System.out.println(prim(9, edges, 0, chosen));
        StringBuilder sb = new StringBuilder("[");
        for (int i = 0; i < chosen.size(); i++) {
            int[] e = chosen.get(i);
            sb.append(i > 0 ? ", " : "").append("(").append(e[0]).append(", ").append(e[1]).append(", ").append(e[2]).append(")");
        }
        System.out.println(sb.append("]"));
    }
}
#include <functional>
#include <iostream>
#include <queue>
#include <tuple>
#include <utility>
#include <vector>
using namespace std;

// Minimum spanning tree by growing one tree from start; returns its weight, fills chosen in order.
int prim(int n, const vector<tuple<int, int, int>>& edges, int start, vector<tuple<int, int, int>>& chosen) {
    vector<vector<pair<int, int>>> adj(n);           // (weight, neighbour)
    for (auto [u, v, w] : edges) { adj[u].push_back({w, v}); adj[v].push_back({w, u}); }
    vector<bool> inTree(n, false);
    // (edge weight, vertex, the tree vertex it hangs from), smallest first
    priority_queue<tuple<int, int, int>, vector<tuple<int, int, int>>, greater<>> pq;
    pq.push({0, start, -1});
    int total = 0;
    while (!pq.empty()) {
        auto [w, v, from] = pq.top(); pq.pop();      // the cheapest edge leaving the tree
        if (inTree[v]) continue;                     // both ends already in the tree: skip
        inTree[v] = true;
        total += w;
        if (from != -1) chosen.push_back({from, v, w});
        for (auto [w2, x] : adj[v])
            if (!inTree[x]) pq.push({w2, x, v});
    }
    return total;
}

int main() {
    vector<tuple<int, int, int>> edges = {{0, 1, 4}, {0, 7, 8}, {1, 2, 8}, {1, 7, 11}, {2, 3, 7}, {2, 8, 2}, {2, 5, 4},
        {3, 4, 9}, {3, 5, 14}, {4, 5, 10}, {5, 6, 2}, {6, 7, 1}, {6, 8, 6}, {7, 8, 7}};
    vector<tuple<int, int, int>> chosen;
    cout << prim(9, edges, 0, chosen) << "\n[";
    for (size_t i = 0; i < chosen.size(); i++) {
        auto [u, v, w] = chosen[i];
        cout << (i ? ", " : "") << "(" << u << ", " << v << ", " << w << ")";
    }
    cout << "]\n";
}

Output: total weight 37, the same as Kruskal, with the edges in the order the tree grew: (0, 1, 4), (1, 2, 8), (2, 8, 2), (2, 5, 4), (5, 6, 2), (6, 7, 1), (2, 3, 7), (3, 4, 9). The tree differs from Kruskal's in one edge (1–2 instead of 0–7, both weight 8): two different minimum spanning trees with equal total.

When to use it

  • Dense graphs (many edges per vertex): with an adjacency matrix and a plain array of best edges, Prim is \(O(V^2)\) with no heap and no sorting, which beats Kruskal's \(O(E \log E)\) when \(E \approx V^2\).
  • Points in the plane where every pair is an edge: the \(O(V^2)\) version needs no edge list at all.
  • When you want the tree to grow from a chosen place, for example a network built outwards from a power station.

Common mistakes

  • Using the distance from the start as the key (that is Dijkstra) instead of the edge weight.
  • Not skipping vertices already in the tree when they are popped again.
  • Disconnected graphs: only the start's component is spanned; check that all \(V\) vertices joined.

Going deeper

Each part below starts closed; open the ones you want.

Sample walkthrough: from vertex 0
Tree so far Cheapest edge leaving it Add Total
{0} 0–1 (4) 1 4
{0, 1} 1–2 (8) or 0–7 (8): tie, the heap picks 1–2 2 12
{0, 1, 2} 2–8 (2) 8 14
{0, 1, 2, 8} 2–5 (4) 5 18
{.., 5} 5–6 (2) 6 20
{.., 6} 6–7 (1) 7 21
{.., 7} 2–3 (7) 3 28
{.., 3} 3–4 (9) 4 37
The math: correctness and running time

Correctness. Let \(S\) be the vertices in the tree. Prim adds a lightest edge crossing the cut \((S, V \setminus S)\), and no tree edge crosses that cut, so by the cut property (proved on the Kruskal page) the tree stays inside some minimum spanning tree at every step. After \(V-1\) additions it is one.

Time with a binary heap. Every edge is pushed at most twice (once from each end) and popped at most twice: \(O(E)\) heap operations of \(O(\log E) = O(\log V)\) each, so \(O(E \log V)\).

Time with an array. Keep best[x] = the lightest edge from the tree to \(x\). Each step scans all \(V\) entries for the minimum and updates the new vertex's neighbours: \(V\) steps of \(O(V)\), so \(O(V^2)\), which is optimal for dense graphs since the input itself has size \(\Theta(V^2)\).

With a Fibonacci heap: \(O(E + V \log V)\).

Cycle property (the mirror image): the heaviest edge on any cycle, if strictly heaviest, is in no MST.

Watch it step by step

Green vertices are in the tree; blue edges wait in the heap; purple edges are in the tree.

Variations and related ideas
  • Jarník described the algorithm in 1930, Prim in 1957 and Dijkstra in 1959, so it is also called the Jarník or Prim–Jarník algorithm.
  • Euclidean MST: for points in the plane, the MST is a subgraph of the Delaunay triangulation, so it can be found in \(O(n \log n)\).
  • MST-based maze generation: Prim on a grid with random weights draws a maze.

See also

References

  • R. C. Prim, "Shortest connection networks and some generalizations", Bell System Technical Journal 36(6), 1957.
  • V. Jarník, "O jistém problému minimálním", Práce Moravské Přírodovědecké Společnosti 6, 1930.
  • T. H. Cormen et al., Introduction to Algorithms, 4th ed., Chapter 21 (minimum spanning trees).